Stage 1 Build Costing

Nana Bambi's โ€” Document Viewer

โ† Back โฌ‡ Download
Viewing: NanaBambis_Stage1_Costing.xlsx โ€” opened in-browser for easy review. Use the download button above if you need the original file.
Stage 1 Summary
Reefer Containers
Reduced Slab
Earth Rampart
Manager Residence
Water System
Electrical & Power
Temp Ops + Security
NANA BAMBI'S โ€” STAGE 1 BUILD COSTING
Stage 1: Live ยท Work ยท Start Operations | Ragay, Camarines Sur | March 2026
4ร— reefers + rampart + residence + slab + utilities + temp operations. No restaurant. No butcher. No hub structure.
SectionStage 1 Cost โ‚ฑNotes
4ร— Reefer Hi-Cube Containers + Transport860,000Cold storage operational from day one
Reduced Slab โ€” rampart/reefer footprint only245,000~140mยฒ โ€” not full building footprint
Earth Rampart + Access Ramp466,400Full rampart โ€” structural + water + garden
Water System418,000Full โ€” tanks, wells, pumps, filtration
Electrical & Power627,000Full โ€” solar, batteries, generator
Drainage โ€” site + slab107,000Full from day one
Manager's Residence โ€” 117mยฒ on poles1,470,5973 bed/2 bath + small kitchen
2ร— 40ft Dry Containers โ€” Temp Logistics Hub160,000Future car park area โ€” redeploys to farm
2ร— 40ft Dry Containers โ€” Fly Camp220,000Staff/worker accommodation on site
Hoop House โ€” 20m ร— 10m185,000Operational cover โ€” redeploys to farm
Perimeter Fencing + Basic Security120,000Site security from day one
Access Track โ€” compacted limestone85,000Basic vehicle access to site
STAGE 1 TOTAL4,963,997Excl. land (โ‚ฑ4.5M held in Family Trust)
WHAT THIS BUYS: A place to live. A place to work. Cold storage operational. Temp operations running. Everything else staged as revenue builds.
Blue values = editable estimates. Replace with actual contractor quotes.
REEFER CONTAINERS โ€” STAGE 1 (4ร— ONLY)
Cold storage operational. Upper floor spine containers (2ร—) are Stage 2 with the restaurant.
ItemQtyUnit โ‚ฑNotes
4ร— REEFER HI-CUBE โ€” REAR COLD STORAGE
40ft reefer hi-cube โ€” cool room 1 (2ยฐโ€“4ยฐC)1185,000Fresh meat, dairy, vegetables
40ft reefer hi-cube โ€” cool room 2 (2ยฐโ€“4ยฐC)1185,000Overflow / market stock
40ft reefer hi-cube โ€” freezer 1 (โˆ’18ยฐC)1185,000Frozen meat, seafood, bulk
40ft reefer hi-cube โ€” freezer 2 (โˆ’18ยฐC)1185,000Overflow + ice production
TRANSPORT & PLACEMENT
Lowboy transport โ€” Naga or Manila to site160,0004 containers, one mobilisation
Crane hire โ€” placement + levelling130,000Position all 4 on rampart
REMOTE REFRIGERATION โ€” COLD CHAIN OPERATIONAL
Remote refrigeration unit โ€” cool room 11120,000Standalone compressor
Remote refrigeration unit โ€” cool room 21120,000
Remote refrigeration unit โ€” freezer 1 (โˆ’18ยฐC)1150,000
Remote refrigeration unit โ€” freezer 2 (โˆ’18ยฐC)1150,000
Refrigeration install + pipework + gas charge150,000Local contractor
Temperature monitoring โ€” digital sensors + alarm115,000All 4 rooms
Strip curtains + door seals115,000
Cool room racking + fit-out217,500Both cool rooms
Freezer racking + fit-out215,000Both freezers
2ร— upper floor spine containers (restaurant structure) are Stage 2.
GROUND SLAB โ€” REDUCED STAGE 1 FOOTPRINT
~140mยฒ under rampart/reefer zone only. Full 277mยฒ poured when restaurant build begins.
ItemQtyUnit โ‚ฑNotes
Ready-mix concrete โ€” 21mยณ @ โ‚ฑ5,500/mยณ1115,500140mยฒ ร— 150mm
BRC mesh reinforcement149,000Full slab coverage
Formwork + edge boarding116,000
Gravel sub-base 100mm111,200
Vapour barrier15,000
Labour โ€” pour and finish128,000
Floor drains ร— 2 with sumps25,500Drainage from day one
Curing and sealing110,000
Stage 2 slab extension: remaining ~137mยฒ poured when butcher/ops fit-out begins. Leave reinforcement starter bars at slab edge.
EARTH RAMPART + ACCESS RAMP โ€” FULL BUILD STAGE 1
Full rampart required in Stage 1 โ€” it IS the foundation for reefers, water tanks, and residence access.
ItemQtyUnit โ‚ฑNotes
RAMPART BODY + RAMP โ€” 1:10 grade, 29m run ร— 4m wide
Fill material โ€” approx. 800 tonnes800150Build up rampart body + ramp
Compaction labour135,000Layer by layer โ€” critical
Sub-surface drainage under ramp140,000CRITICAL โ€” prevents waterlogging
Concrete ramp surface โ€” 116mยฒ116400Non-slip, gentle gradient
CHB retaining walls โ€” both sides1120,000Contain fill, define edges
Trellis wall + raised garden beds over tanks180,000Conceals tanks, grows kitchen herbs
Path lighting โ€” low bollards125,000Guest arrival experience
EXTERNAL STAIRS โ€” left wing, staff + delivery access
Steel stringers + landing plate145,000Rise ~2.9m
Hardwood/bamboo treads + nosings128,000
Handrails โ€” both sides122,000
Pad footings ร— 226,000
Labour118,000
MANAGER'S RESIDENCE โ€” 117.3mยฒ ON POLES
3 bed / 2 bath + small kitchen. Light steel + FCB + nipa. Connects to hub when built.
ItemQtyUnit โ‚ฑNotes
STRUCTURE โ€” poles + floor (elevated ~2.9m)
Steel poles ร— 14 + pad footings1412,50017m span
Steel floor frame โ€” joists117500Per mยฒ floor area
19mm FCB floor deck117380
Connection point โ€” future hub doorway125,000Beam + opening ready for Stage 2
WALLS โ€” light steel stud + FCB + nipa cladding
External wall frame โ€” light steel stud1122,607
Internal partition walls159,823Per plan
Nipa external cladding over FCB177,436Matches future hub aesthetic
ROOF โ€” torch-on membrane + nipa (141mยฒ actual)
Steel rafters + purlins117700
19mm FCB deck141280141mยฒ actual on pitch
Torch-on base sheet + cap sheet141770Two-layer sealed system
Batten grid + nipa panels141630Air gap + finish
Ridge + gutters + downpipes160,000
Labour โ€” membrane + nipa117400
FIT-OUT
Ensuite โ€” bed 1165,000Full bathroom
Bathroom + WC โ€” main155,000
Laundry125,000
WIR fit-out โ€” bed 1115,000
Bedrooms ร— 3 โ€” storage + fans + screens320,000
Living/dining โ€” floor, ceiling, lights135,000
Doors + windows + fly screens160,000Per Selecta plan spec
Electrical โ€” sub-board + full fit-out140,000
Plumbing โ€” bathrooms + laundry + kitchen145,000Includes kitchen plumbing
Private stairs to garden/rampart112,000
SMALL KITCHEN โ€” functional domestic, Stage 1 only
Kitchen cabinets โ€” upper + lower run135,000Basic flat-pack or local joinery
Benchtop โ€” 3m laminate or timber115,000
4-burner gas hob + LPG connection118,000
Under-bench fridge112,000Secondhand
Double bowl sink + tapware112,000
Rangehood18,000
Kitchen is Stage 1 only โ€” becomes prep/breakfast kitchen when restaurant connects. Corporate asset, part of CEO salary package.
WATER SYSTEM โ€” FULL STAGE 1
Full water system required Stage 1. Tanks on rampart gravity-feed residence + cold storage.
ItemQtyUnit โ‚ฑNotes
Poly tanks โ€” 30,000L ร— 3 = 90,000L on rampart366,000Gravity-fed โ€” no pumps
Well drilling ร— 2240,000Hub site + big farm
Pump systems ร— 3315,000Submersible + lift
Filtration โ€” potable multi-stage125,000Clean drinking water
Pipe & fittings โ€” full network130,000Residence + reefers + hoop house
Pump control room (build)140,000Standalone structure
River lift pump โ€” big farm135,000Uphill from river
Solar pump fills tanks from well daily. Gravity feeds residence, reefers, hoop house, fly camp.
ELECTRICAL & POWER โ€” FULL STAGE 1
Full system required Stage 1. Cold storage is 24/7 load โ€” cannot cut corners on power.
ItemQtyUnit โ‚ฑNotes
Solar panels + rotating axis mount1120,000Primary power source
LiFePO4 battery bank1150,000Storage โ€” overnight + cloud cover
Charge controllers + inverter140,000
Diesel generator โ€” 3-phase backup180,000Brownout + extended outage backup
20ft electrical hub container1120,000Switchboard + meter room
Sub-boards ร— 4 zones48,000Reefers / residence / temp ops / site
Wiring + conduit โ€” Stage 1 scope145,000Residence + reefers + fly camp + hoop
Isolation switches โ€” flood rated43,000High placement
Shade cladding for electrical hub115,000Roof + air gap
Cold storage is the critical load โ€” 4 remote refrigeration units running 24/7. Monthly est. โ‚ฑ15,000 running cost.
TEMPORARY OPERATIONS โ€” CONTAINERS + HOOP HOUSE
All assets redeploy to farm when hub is built.
ItemQtyUnit โ‚ฑNotes
2ร— 40ft DRY CONTAINERS โ€” TEMP LOGISTICS HUB
40ft dry container ร— 2255,000Japan surplus or Manila yard
Container transport + placement125,000
Basic shelving + pallet racking120,000
Power connection โ€” sub-board18,000
Roller door upgrade โ€” one container112,000Easy forklift access
2ร— 40ft DRY CONTAINERS โ€” FLY CAMP
40ft dry container ร— 2255,000
Container transport + placement120,000
Basic fit-out โ€” bunks, lockers, ceiling fans220,000Per container
Basic ablutions โ€” wet room fit-out135,000One container partitioned
Power + lighting + fans28,000Per container
Window/vent cuts + louvres43,500Cross ventilation
HOOP HOUSE โ€” 20m ร— 10m = 200mยฒ
Galvanised steel hoop structure1120,000200mยฒ covered area
Heavy-duty poly cover + UV stabilised135,000
End wall closures118,000Vehicle access one end
Concrete strip footings for hoops112,000
SITE ACCESS + SECURITY
ACCESS TRACK
Limestone โ€” basic vehicle access track155,000From road to site
Grading + compaction120,000
Basic drainage either side110,000
PERIMETER FENCING + SECURITY
Perimeter fencing โ€” full site1120,000
Site gate โ€” vehicle rated115,000
Basic CCTV ร— 4 cameras125,000Key zones only Stage 1
Site lighting โ€” key areas110,000